UST Program - Marina Fuel Storage and Piping Inspection Form Instructions
- Review the Marina Fuel Storage and Piping Inspection Form prior to conducting an inspection.
- The "Facility, Inspector, and General Facility Information" form should be completed for each facility.
- For facilities that have more than one tank system,
a "Tank" form should be completed for each tank. To
document the many changes in piping materials associated
with each tank system, you may need to complete several
of the "Piping" forms. The "Tank" and "Piping" forms
are designed to start the inspection at the tank,
work your way through the piping, and finish at the
dispenser.
- (Example: Bev's Marina has two underground storage tanks systems. Tank System #1 has 4 piping transitions from the tank to the dispenser and Tank System #2 has 7 piping transitions. The following paperwork should be completed:
- One "Facility, Inspector and General Facility Information" form.
- Tank System #1 should have 1 "Tank" form, and 4 "Piping" forms (one for each transition).
- Tank System #2 should have 1 "Tank" form, and 7 "Piping" forms (one for each transition).
- Review the glossary of terms provided. Definitions are provided to ensure that our data gathering effort is consistent.
- Review the diagram of a typical marina for a visual aid.
- Return inspection forms as you complete them. Return all inspection forms by December 31, 2001 to Laura Chaddock, Clean Water Programs, P.O. Box 944212, Sacramento, CA 94244-2120. The inspection form will be available on our webpage at www.waterboards.ca.gov/ust/. Return electronic copies of the inspection form to lchaddock@waterboards.ca.gov.
For technical assistance or questions please contact Ms. Laura Chaddock at (916) 341-5870.