Region 8 (Santa Ana)
Regional Considerations
Facilities
Regulated
Facilities
Inspected
Permits Issued, Revised and Renewed Enforcement (Compliance & Penalty Actions) Budget Staff (PY)
Program Actual Target % Target Actual Target  % Target 
NPDES Major Individual 22 5 13 38% 4 7 57% 0 $1,031,296 8.9
NPDES Minor Individual 11 0 2 0% 0 5 0% 0
NPDES Minor General Enrollees 125 0 18 0% 5 0 NA 0
Stormwater Construction 1193 201 410 49% 299 0 NA 0 $1,597,101 13.4
Stormwater Industrial 1648 145 180 81% 78 0 NA 0
Stormwater Municipal 62 7 2 350% 0 0 NA 0
Waste Discharge to Land, Municipal Waste 36 3 10 30% 0 4 0% 0 $319,728 2.8
Waste Discharge to Land, Industrial Waste 10 0 0 NA 0 0
Waste Discharge to Land, All Other Facilities 20 0 0 NA 0 0
Land Disposal Landfills 27 20 25 80% 11 1 1,100% 0 $518,741 3.7
Land Disposal All Other 30 11 5 220% 6 2 300% 0 $0 0.0
Timber Harvest 0 0 0 NA 0 0 NA 0 $0 0.0
Confined Animal Facilities 143 2 75 3% 0 0 NA 0 $0 0.0
All Other Programs 0 5 29 0 $404,889 3.4
TOTAL 3,327 399 432 0 $3,871,755 32.2