ATTACHMENT A
1998 TRIENNIAL REVIEW PRIORITY LIST
(Highest Priority Issues are Ranked First)
|
TASK |
Type of Action |
ESTIMATED TIME (Staff years and Duration) |
Status |
Comments |
|
Surface Water Issues |
||||
|
1. Develop Region-Wide Nonpoint Source Management Measures |
Policy/BMP |
3 months/ 2 years |
In progress |
|
|
5. Develop Riparian Corridor Protection Policy |
Policy |
2 months |
Broaden to cover wetlands not part of 401 program? Region 2 is developing a document that links beneficial uses to protecting the Riparian corridor. Region 2 will have a final technical document for review before the end of April. Let’s glean what we like from them. |
|
|
18. Develop Water Quality Objectives to Protect Rare, Threatened, or Endangered Species Beneficial Use |
Objective |
6 months/ 1 years |
TMDL’s may identify specific numeric targets, these may be useful as starting points for Water Quality Objectives By protecting the Riparian corridor, you will protect the habitat that species need to survive and reproduce. |
|
|
19. Develop Monitoring Plan for Communities without Sewer Service |
Plan |
8 months |
Part of AB 885 process |
|
|
28. Develop Water Diversion Policy (to address water quality impacts) |
Policy |
2 months |
||
|
29. Clarify Narrative Objective for Taste/Odors and Toxics |
Objective |
4 months |
||
|
51. Develop Narrative Biological Objective/Protect from Dominance of Nuisance Species |
Objective |
2 months |
||
|
53. Revise Turbidity Objective |
Objective |
3 months |
||
|
63. Develop Biomedical Rangeland Policy |
Policy |
9 months |
||
|
64. Determine Beneficial Uses for Arguello Hydrologic Area |
2 months |
|||
|
72. Update On-Site Septic Tank Policy/Update MOUs |
Policy |
9 months |
Part of AB 885 process |
|
|
73. Develop Septic Tank Prohibition for Santa Margarita Area |
Policy |
7 months/ 1 year |
Part of AB 885 process |
|
|
76. Evaluate and Revise “Inorganic” Water Quality Objectives |
Objective |
3 months |
TMDL’s may identify specific numeric targets, these may be useful as starting points for Water Quality Objectives |
|
|
78. Develop Septage Disposal Policy |
Policy |
3 months |
Part of AB 885 process |
|
|
79. Update Waiver Policy/Add Waiver for Green Waste used in Composting |
Policy |
2 months |
||
|
81. Update “Rare” Beneficial Use |
3 months |
|||
|
83. Reevaluate Water Quality Objectives for Irrigation Water |
Objective |
3 months |
||
|
106. Develop Nutrient Water Quality Objectives and Management Measures for Franklin Creek |
Objective |
6 months/ 2 years |
||
|
107. Develop Nutrient Water Quality Objectives and Management Measures for Santa Monica Creek |
Objective |
6 months/ 2 years |
Should this be on 303d list? |
|
|
108. Develop Management Plan for Devereaux Slough |
Plan |
6 months |
||
|
109. Develop Nutrient Objectives and Management Measures for Lopez Lake |
Objective |
6 months/ 2 years |
||
|
110. Develop Boatyard Best Management Practices |
Plan/BMP |
2 months |
See State NPS Plan, Coastal commission efforts, reference in the Basin Plan Bilge water? |
|
|
111. Develop Total Chlorine Residual Objective |
Objective |
1 month |
||
|
112. Develop Ammonia Objective |
Objective |
9 months |
||
|
113. Develop Nutrient Objective and Management Measures for Perfumo Creek |
Objective |
6 months/ 2 years |
In progress – numeric target is a component of the SLO Creek TMDL and management measures are in the TMDL implementation plan. |
|
|
114. Evaluate Cadmium and pH Objective for Fish Spawning |
Objective |
4 months |
DFG, NMFS, and USFW have info about pH and how it affects fish spawning. Check with those agencies. |
|
|
115. Update Table 2-2, “Existing and Anticipated Uses of Coastal Waters” |
Beneficial Uses |
3 months/ 2 years |
||
|
116. Update Monitoring Table in Chapter Six |
Plan |
2 months/ 6 months |
Page VI-6 through VI-9 describes our regional monitoring efforts |
|
|
117. Develop Maintenance/Repair Standards for On-Site Systems |
BMP |
3 months |
Part of AB 885 process |
|
|
118. Update Mound System Guidelines |
Policy |
3 months |
Part of AB 885 process |
|
|
119. Develop Abandoned Mine Policy |
Policy |
4 months |
A sampling policy would be helpful. This way, you can begin to collect consistent data from day one. Draw on Morro Bay NEP effort. Morro Bay, Las Tablas Creek, Pajaro River, and Clear Creek TMDL’s may identify specific numeric targets, these may be useful as starting points for Water Quality Objectives |
|
|
120. Reevaluate Llagas Creek Water Quality Objectives |
Objective |
3 months/ 1 year |
In progress– numeric target is a component of the Pajaro River (includes Llagas Creek) TMDL and management measures will be in the TMDL implementation plan. |
|
|
121. Update Rare, Threatened, or Endangered Species Beneficial Use |
Beneficial Uses |
1 months/ 8 months |
Could we adopt the policies that the USFW, DFG and NMFS use? If you protect the riparian corridor, you protect the beneficial use for those species. |
|
|
122. Update Beneficial Uses |
Beneficial Uses |
1 month/ 8 months |
New BU’s: Water Fowl Hunting (Elkhorn Slough) Groundwater Recharge – Salinas Rec. Canal? |
|
|
123. Develop Horse Coral Best Management Practices |
BMP |
2 months |
319h grant/contract issued to SLR RCD March 2001 – Implementation in progress |
|
|
124. Determine Appropriate Beneficial Uses for Carizzo Plain Ground Water Basin |
Beneficial Uses |
6 months/ 1 year |
||
|
125. Add “Ground Water Recharge” Beneficial Use to Watsonville/Harkins Slough |
Objective |
1 month |
||
|
126. Update State Board Policies |
Policy |
2 months |
Link to Triennial Review priority number one, address adoption of CTR |
|
|
127. Update Municipal Facilities Plans |
Plan |
4 months |
Review Basin Plan Chapter IV |
|
|
128. Develop Auto Wrecking Yard Policy |
Policy |
4 months |
The State Storm Water Program requires industries with Standard Industrial Classification Codes 5015 (Motor Vehicle Parts, Used) and 5093 (Scrap and Waste materials) to obtain permits from the Regional Board. The State Storm Water Permit requires the industries above to create a site specific Storm Water Pollution Prevention Plan (SWPPP). The SWPPP only accounts for impacts to surface water bodies. Impacts to ground water such as leaking oil sumps are not accounted for in the Storm Water Program. Policy may need to be drafted for impacts to groundwater. |
|
|
129. Develop Greenhouse Policy |
Policy |
4 months |
||
|
130. Develop Low Threat to Water Quality Policy for Surface Water |
Policy |
2 months |
Status? |
|
|
131. Evaluate Need for Bacteria Objective for Ocean Waters Used for Desalination Water Supply/Consider Appropriateness or MUN designation |
Objective |
6 months |
||
|
132. Assess Problems at Shooting Ranges and Develop Management Measures |
Assessment/ Plan |
3 months/ 2 years |
||
|
133. Develop Aquaculture Management Plan |
Plan |
3 months |
|
TASK |
Type of Action |
ESTIMATED TIME (Staff years and Duration) |
Status |
Comments |
TMDL Issues |
||||
|
2. Develop Carbonara Creek, Lompico Creek, and San Lorenzo River Nutrient TMDL |
6 months |
Adopted by RWQCB 9/15/2000 |
||
|
3. Develop San Luis Obispo Creek Nutrient TMDL |
6 months |
Draft technical TMDL to EPA 6/2000 |
Revised TMDL to be completed 6/2002 |
|
|
7. Develop Chorro Creek, Los Osos Creek, and Morro Bay Siltation Total Maximum Daily Load |
3 months/ 2 years |
Draft TMDL to EPA/Stakeholders 11/2000 |
Revisions to be completed 6/2001 and sent to Board 6/2002. |
|
|
8. Develop Las Tablas Creek; Las Tablas Creek, North Fork; Las Tablas Creek, South Fork; and Nacimiento Reservoir for Mercury TMDL |
4 months/ 2 years |
Draft TMDL to EPA 6/2000 |
Revisions to be completed 6/2001 and sent to Board 6/2002. |
|
|
10.a. Develop Chorro Creek Metals TMDL |
3 months/ 2 years |
Draft TMDL to EPA/Stakeholders 04/2001 |
Revisions to be completed 6/2001 and sent to Board 6/2002. |
|
|
10.b. Develop Morro Bay Metals TMDL |
3 months/ 2 years |
Monitored assessment initiated 03/2001 |
To be done 6/2002 |
|
|
11. Develop Chorro Creek and Los Osos Creek Nutrient TMDL |
3 months/ 2 years |
Draft TMDL to EPA/Stakeholders 02/2001 |
Revisions to be completed 6/2001 and sent to Board 6/2002. |
|
|
13. Develop Los Osos Creek Priority Organics TMDL |
3 months/ 2 years |
Monitored assessment initiated 03/2001 |
Revisions to be completed 6/2001 and sent to Board 6/2002. |
|
|
14. Develop Morro Bay Pathogen TMDL |
3 months/ 2 years |
Problem statement and numeric target to EPA 6/2000 |
DNA study to be completed 09/2001 Revisions to be completed 12/2001 and sent to Board 12/2002. |
|
|
15. Develop Carbonara Creek, Lompico Creek, San Lorenzo River, and San Lorenzo River Estuary Siltation TMDL |
4 months/ 2 years |
Internal Draft TMDL completed 03/2001 |
Revisions to be completed 6/2001 and sent to Board 6/2002. |
|
|
21. Develop San Luis Obispo Creek Pathogen TMDL |
6 months/ 2 years |
Monitored assessment initiated 03/2001 |
To be done 12/2002 |
|
|
22. Develop Aptos Creek and Valencia Creek Siltation TMDL |
6 months /5 years |
Monitored assessment initiated 03/2001 |
To be done 6/2002 |
|
|
23. Develop Soquel Lagoon Siltation TMDL |
4 months/ 5 years |
|||
|
24. Develop Salinas River and Salinas River Lagoon (North) Siltation TMDL |
1 year /3 years |
Problem statement to EPA 6/2000 |
Technical support for TMDL contracted out on 09/2000 |
|
|
25. Develop Carbonara Creek, Lompico Creek, and San Lorenzo River Estuary Pathogen TMDL |
4 months/ 3 years |
Coordinating with Santa Cruz County regarding studies needed and establishing a schedule. |
||
|
26. Develop Pajaro River Nutrient TMDL (includes Llagas Creek) |
1 year/ 3 years |
Problem statement in progress |
Stakeholder meetings initiated 03/2001 |
|
|
27. Develop Pajaro River Siltation TMDL (includes Llagas Creek, Rider Gulch Creek, and San Benito River) |
1 year/ 3 years |
Problem statement in progress |
TMDL to be contracted out 06/2001 |
|
|
30. Develop Watsonville Slough Siltation TMDL |
3 months/ 3 years |
To be included in the Pajaro River siltation TMDL, No. 27 above |
||
|
33. Develop San Luis Obispo Creek Priority Pollutant TMDL |
6 months/ 3 years |
Monitored assessment initiated 03/2001 |
To be done 6/2003 |
|
|
34. Develop Old Salinas River Estuary, Salinas River, Salinas River Lagoon (North), and Salinas River Lagoon (South) Nutrient TMDL |
1 year 5 years |
Preliminary Literature review 10/2000 |
||
|
35. Develop Espinosa Slough and Tembladero Slough Nutrient TMDL |
4 months/ 5 years |
To be done 6/2003 |
||
|
36. Develop Old Salinas River Estuary, Salinas River, Salinas River Lagoon (North), and Salinas River Lagoon (South) Pesticides/Priority Organics TMDL |
4 months/ 5 years |
Preliminary Literature review 10/2000 |
||
|
37. Develop Espinosa Slough, Moro Cojo Slough, and Tembladero Slough Pesticides/Priority Organics TMDL |
4 months/ 7 years |
To be done 6/2003 |
||
|
38. Develop Salinas River and Salinas River Lagoon (South) Salinity/TDS/Chlorides TMDL |
1 year/ 7 years |
Preliminary Literature review 10/2000 |
||
|
39. Develop Clear Creek and Hernandez Reservoir Mercury TMDL |
1 year/ 7 years |
Preliminary Literature review 10/2000 |
Problem statement to be developed by 06/2001 |
|
|
40. Develop Watsonville Slough Metals TMDL(10/06-04/07) |
3 months/ 7 years |
Literature review in progress |
Preliminary problem statement to be developed by 06/2001 |
|
|
41. Develop Watsonville Slough Oil and Grease TMDL |
3 months/ 7 years |
Preliminary Literature review 10/2000 |
Preliminary problem statement to be developed by 06/2001 |
|
|
42. Develop Watsonville Slough Pathogens TMDL |
3 months/ 7 years |
|||
|
43. Develop Watsonville Slough Pesticide TMDL |
3 months/ 7 years |
Literature review in progress |
Preliminary problem statement to be developed by 06/2001 |
|
|
44. Develop Monterey Harbor and Monterey Bay South Metals TMDL |
9 months/ 7 years |
|||
|
45. Develop Blanco Drain and Salinas Reclamation Canal Pesticide/Priority Organics TMDL |
4 months /8 years |
Problem statement to be developed by 06/2001 |
||
|
56. Develop Santa Ynez River Nutrient TMDL |
1 year/ 7 years |
|||
|
57. Develop Santa Ynez River Salinity/TDS/Chlorides TMDL |
1 year/ 7 years |
|||
|
58. Develop Santa Ynez River Siltation TMDL |
1 year/ 7 years |
|||
|
59. Develop Elkhorn Slough and Moss Landing Harbor Pesticides TMDL |
4 months/ 8 years |
|||
|
60. Develop Elkhorn Slough and Moss Landing Harbor Siltation TMDL |
4 months/ 8 years |
|||
|
61. Develop Moro Cojo Slough Siltation TMDL |
6 months/ 5 years |
|||
|
62. Develop Aptos Creek and Valencia Creek Pathogen TMDL |
6 months/ 8 years |
|||
|
84. Develop Schwan Lake Pathogen TMDL |
6 months/ 8 years |
|||
|
85. Develop Soquel Lagoon Pathogen TMDL |
4 months/ 8 years |
|||
|
86. Develop Schwan Lake Nutrient TMDL |
6 months/ 8 years |
|||
|
87. Develop Soquel Lagoon Nutrient TMDL |
4 months/ 8 years |
|||
|
88. Develop Waddell Creek, East Branch Nutrient TMDL |
1 year/ 8 years |
|||
|
89. Develop Arroyo Burro Creek Pathogen TMDL |
1 year/ 8 years |
|||
|
90. Develop Carpinteria Creek Pathogen TMDL |
1 year/ 8 years |
|||
|
91. Develop Goleta Slough/Estuary Pathogen TMDL |
3 months/ 8 years |
|||
|
92. Develop Mission Creek Pathogen TMDL |
6 months/ 8 years |
|||
|
93. Develop Pacific Ocean at Rincon Creek Pathogen TMDL |
1 year/ 8 years |
|||
|
94. Develop Carpinteria Marsh Nutrient TMDL |
3 months/ 8 years |
|||
|
95. Develop Carpinteria Marsh Organic Enrichment/Low Dissolved Oxygen TMDL |
3 months/ 8 years |
|||
|
96. Develop Carpinteria Marsh Priority Organics TMDL |
3 months/ 8 years |
|||
|
97. Develop Carpinteria Marsh Siltation TMDL |
3 months/ 8 years |
|||
|
98. Develop Goleta Slough/Estuary Metals TMDL |
3 months/ 8 years |
|||
|
99. Develop Goleta Slough/Estuary Priority Organics TMDL |
3 months/ 8 years |
|||
|
100. Develop Goleta Slough/Estuary Siltation TMDL |
3 months/ 8 years |
|||
|
101. Develop San Antonio Creek Siltation TMDL |
1 year/ 8 years |
|||
|
102. Develop Mission Creek Toxicity TMDL |
6 months/ 8 years |
|||
|
103. Develop Elkhorn Slough and Moss Landing Harbor Pathogen TMDL |
4 months/ 8 years |
|||
|
104. Develop Monterey Harbor Toxicity TMDL |
1 year/ 8 years |
|||
|
105. Develop Monterey Bay South Pesticide TMDL |
1 year/ 8 years |
|
TASK |
Type of Action |
ESTIMATED TIME (Staff years and Duration) |
Status |
Comments |
|
Ground Water Issues |
||||
|
4. Determine Objective Compliance for Ground Water Basins/Propose Monitoring Plan and Remedial Measures |
Objective |
5 years |
Develop objectives for Eastside and Shallow aquifers in the Salinas basin. |
|
|
6. Develop Monterey County Aquifer Storage and Recovery Policy |
Policy |
4 months |
||
|
9. Develop Nitrogen Management Plan for Salinas Ground Water Basin |
Plan |
9 months 2 years |
||
|
12. Develop Water Softener Use Policy -- Region-Wide |
Policy |
6 months |
||
|
16. Develop Nitrogen Management Plan for Llagas/Hollister Ground Water Basin |
Plan |
9 months/ 2 years |
||
|
17. Develop Nitrogen Management Plan for Prunedale Ground Water Basin |
Plan |
6 months/ 2 years |
||
|
20. Determine Ground Water Protective Measures for Sensitive Ground Water Resources |
BMP |
6 months |
||
|
31. Develop Nitrogen Management Plan for Santa Maria Ground Water Basin |
Plan |
6 months/ 2 years |
||
|
32. Develop Nitrogen Management Plan for Pajaro Ground Water Basin |
Plan |
6 months/ 2 years |
||
|
46. Develop Ground Water Cleanup Policy |
Policy |
6 months |
||
|
47. Develop Soil Cleanup and Disposal Policy/Develop Area -Wide Objectives |
Objective |
6 months |
||
|
48. Develop Shallow Ground Water Policy/Determine Appropriate Beneficial Uses |
Beneficial Uses |
1 year |
||
|
50. Develop Oilfield Waste Policy |
Policy |
3 months |
||
|
52. Develop Backflow Prevention Policy |
Policy |
3 months |
||
|
54. Develop Nitrogen Management Plan for Paso Robles Ground Water Basin |
Plan |
6 months/ 2 years |
||
|
55. Develop Nitrogen Management Plan for Arroyo Grande Ground Water Basin |
Plan |
6 months/ 2 years |
||
|
65. Develop Nitrogen Management Plan for San Luis Obispo Ground Water Basin |
Plan |
6 months/ 2 years |
||
|
66. Develop Nitrogen Management Plan for Cuyama Ground Water Basin |
Plan |
6 months/ 2 years |
||
|
67. Develop Nitrogen Management Plan for Carrizo Ground Water basin |
Plan |
6 months/ 2 years |
||
|
68. Develop Nitrogen Management Plan for Santa Ynez Ground Water Basin |
Plan |
6 months/ 2 years |
||
|
69. Develop Ground Water Objectives for Llagas/Hollister Ground Water Basin |
Objective |
4 months/ 2 years |
||
|
70. Develop Nitrogen Management Plan for Chorro Ground Water Basin |
Plan |
4 months/ 2 years |
||
|
71. Develop Nitrogen Management Plan for Seaside Ground Water Basin |
Plan |
4 months/ 2 years |
||
|
74. Develop Paso Robles Ground Water Basin Management Plan |
Plan |
3 months |
Improve beneficial use designations Address geothermal issues |
|
|
75. Develop Nitrogen Management Plan for Scotts Valley Ground Water Basin |
Plan |
4 months/ 2 years |
||
|
77. Develop Well Abandonment Policy |
Policy |
1 month |
||
|
80. Develop Ground Water Objectives for Los Osos Ground Water Basin |
Objective |
4 months/ 1.5 year |